finished resin floor

Resin floor in Milan via Teodosio.

Good day!

We want to share with you the latest achievement of our work in Milan. In photographs and videos, we show the complete cycle of work done on the floor-to-floor resin arrangement by microcement. We made a resin flooring deposit on the old ceramic floor.

The total area covered about 120 square meters.

We've completed all the work in 5 business days.

Start date June 26, 2017.

The completion date is June 30, 2017.